Sunday, September 16, 2012

Powdering my nose...

Here's the first of many room reveals...Its not a biggie, but rather one of the three 'little rooms' in our new home.

Presenting............ the Powder Room!


Cabinetry is New Graphite Laminex with Contour Edge. 
Benchtop is Ice Snow Caesarstone.

Lovely orchids from local florist
Gorgeous Glasshouse candle - Amalfi Coast.
Orrefors Bowl that I have had for years and fits in so well.

Vito Bertoni "Vito" wall mount tap set.
Fowler Regent semi inset basin
Divine Aesop hand wash and moisturising balm
(Cam said to me before he was unsure which one to use and he just wanted the bottle to say "Soap" LOL!!!!)

PLUS... A cute little hand towel I picked up for a song at Turner and Lane in South Yarra.

Fowler Regent Toilet Suite with all important soft close mechanism. I'm hoping the novelty of the soft close will be incentive for my boys to put the toilet seat down.

More soon, we promise. We are waiting for a few more things for the dining/kitchen and then we will reveal them in all their glory :)

Kirst xxx





Wednesday, September 12, 2012

Moving with the times...

Hiya peeps, we are still here. 

We moved into our place on Monday and it has been absolute chaos. 

We are nearly finished cleaning the rental we were in, the landscapers are working on the front and side retaining walls and half of the house is unpacked.

It has been a flurry of activity and we are loving the new house so far!

Stay tuned for some photos in the next few days...

Kirst

Monday, September 3, 2012

Jingle Jangle...

Is that a key in your pocket? or are you just happy to see me?

This afternoon, 20 months after we began this blog and 343 days since site start, we finally got the keys to our new Metricon HOME!



There is still a bit of rubbish on site that is being cleaned up tomorrow. Along with a leaky connection to the hot water service also being fixed first thing tomorrow. But overall the quality of the house is really good.

Like everyone else, here is the little gift we got from Metricon.

It is finally OURS!!!

We are planning on moving next Monday. Landscapers start tomorrow. This week will be a flurry of deliveries, our own tradies, cleaning (the builders clean is pretty lame) and packing up the rental.

So busy but so exciting! Tonight we are off to celebrate with Pizza and gear up for Lachie's operation tomorrow, he requested Pizza as his last meal before fasting. Wish us well!

Kirst and Cam
xxx

Monday, August 27, 2012

Pergatory ? ?

All of you in bloggyland are probably wondering what's going with us and our new home at the moment.

WE ARE IN PURGATORY/LIMBO/HALFWAY BETWEEN HEAVEN AND HELL!

4 days after PCI we were informed by our SS that there was no way we would have handover last Friday, despite the discussions we had with him at our inspection. Apparently a replacement door for the garage access was unavailable until Tuesday (tomorrow)! And in the last week not much has really happened as far as we can see.

We were told in no uncertain terms that we should not even expect to hear from our SS for another week and that his previous comments about definitely being given the keys by the end of the month no longer stood.  Unbelievable,  especially given we enquired about a realistic chance of handover within the month of August as we had to give notice on our rental - this was also made known to him.


At least SS has been true to one of his words and we have not heard hide nor hair from him for a whole week. This close to handover, to say we are devastated and frustrated is an understatement. 



It also appears our SS is dragging his feet purposely, having told Cam in a previous conversation that "he could make the process go as slow or as fast as he wants". We have flagged this unprofessional comment with our CSC who suggested that the best course of action was to speak with our CM. We have left him both email and voice messages and heard nothing. Another example of the poor communication that seems to be rife in this company (see previous post HERE). 



It has been 336 days since we first turned dirt. That's over 11 months and a far cry from the 8 months we were told by numerous SALES staff from Metricon.  

Tip to the new players: Don't believe the sales pitch or get the unrealistic build time written into your contract.



So we have given notice on our rental and need to be out by the first week of September. On top of this, Lachie (our 4 year old) is going to have his tonsils out in a weeks time. STRESSFUL... you betcha.


Watch this space. I hope to have some good news soon.

Kirsten
xxx

Friday, August 17, 2012

Give me a P, Give me a C, Give me an I....

That's right folks... this morning we finally had our PCI and things are looking promising!

We met SS and our Independent Inspector, Rob from Building Check, on site at 8am this morning. It was a huge relief to know that there only remain small touch-ups and minor fixes that can be completed quickly. It was also a novelty that our SS was on the phone arranging trades as each issue was picked up and most are booked in for next Monday through Wednesday.

Our Independent Inspector was overall impressed with the quality of the workmanship in our house, which is great to know. In essence the following need completing before handover... 

  • The lines in the carpets that we mentioned HERE have not resolved themselves. The downstairs carpets are all being replaced on Tuesday, but the company still believes that the upstairs carpet will resolve and if not are writing us a letter to confirm that they will be responsible for replacing it if it still has lines in a few months time including moving the furniture if required.
  • Our inspector discovered that the heating vent in the ceiling connecting the master bedroom heating to the rest of the house has been disconnected by a careless tradie. Luckily the heating guys are coming on Wednesday to commission the heating system and will fix it then.
  • We discovered that the pop up bath wastes were not installed. After a quick call to the plumber, it was revealed that they were not able to be installed because of the order in which the bath was installed 3 months ago and no one bothered to say anything. Now the only way to have the pop up wastes is to access the bath plumbing from below ie cut the ceiling in the rumpus and the sitting room, connect the waste and patch it all up again... but the SS assured us that it wouldn't add much if any days.
  • Flashing to go on top of the external brick firebox which was recommended when our Independent Inspector came in April still has not been completed. It is needed to stop moisture coming through the porous bricks on the top and getting into the Jetmaster... we couldn't have that could we? What is a mystery (even after directly asking our SS this question!) is why something picked up in April still needs to be done and more importantly how it can pass the QA process.
  • Other bits and bobs include a new microwave which was on back order, the elusive colander and chopping board for sink, paint touch-ups, silicon fix ups, grout cleaning, dampers on exhaust fans (which were on 2/5), hot water service needs alteration so that the valve is safer, external garage door replacement and lock.

Exciting times ahead! We are expecting a call from SS on Tuesday afternoon to book in Handover for next FRIDAY!

Pray to the handover gods for us!

Kirst
xxx

Monday, August 13, 2012

fiddy tousand!

No, I haven't gone bonkers waiting for handover and started making gangsta moodboards to furnish the lounge room...

Instead dear readers, we've reached another milestone... 

50,000 clicks (50,776 actually)

In reality I'd be happy with a set of keys. Good things come to those who wait I'm told.

Kirst

Tuesday, August 7, 2012

Waiting waiting waiting......

Dropped by our soon to be new home and noticed a few of the QA items appeared to have been at least started. While there, the SS arrived so I asked about our list of items we (both the SS and us) know need to be rectified pre handover. Many of the items have been with the SS for sometime to action, so heaven only knows why they are only being addressed now and why the original QA didn't pick then up. Anyway, that's another topic.

Due to the weather Melbourne has had recently our second QA wont occur this Friday. Waiting on the renderers to redo some of the front facade. So we have had to push our PCI ( with our independent inspector ) til next Friday. Hoping handover will be a few days after then...

On matters within our control, we have engaged a concreter and landscaper to crack into work as soon as we have handover although likely to start prior to that given the delays we have had. More about them later on. We are wanting the hardscape work done prior to moving in.

Hopefully something more productive to talk about next time.

Cam